June Construction Update (2019)
East Side: Vertical drilling for shoring is complete. Three of five cranes are erected on site. The last two cranes will go up late July/early August and mid-September, respectively. Excavation and foundation work is ongoing on the north half of the property. Final excavation work is expected for September.
West Side: Vertical drilling for shoring is complete with the exception of the tunnel connecting to the east side. Excavation is not expected to commence until summer 2020.
Heritage Buildings: Restoration work continues at the Heritage properties. 610 Markham House is likely to be moved in mid-September.